Yes, if your council switches it on. An admin turns on Automatically update routine status in Manage Account → Settings, under Automations. It is off by default. With it on, each routine occurrence moves itself along as the work underneath it is done. With it off, someone marks the routine Done by hand.

Detail

With the setting on, an occurrence of a routine changes status on its own:

  • In Progress when the first task under it is started.
  • Done when every task under it is resolved. A failed inspection counts as resolved, because it was carried out.
  • Cancelled when every task under it is cancelled.
  • Back to In Progress if a task under a Done occurrence is reopened.

Each of these changes is recorded in the routine's history as made by System Automated, so you can tell an automatic update from one a person made.

To switch it on:

  1. Open the app switcher (the four-squares icon, top right) and choose Manage Account.
  2. Click Settings in the left-hand menu.
  3. Under Automations, turn on Automatically update routine status.

The setting applies to the whole council, so only an admin (someone who can manage other users' permissions) can change it.

Watch-outs

  • It only acts on work done after you switch it on. Routines that were already complete when you turn it on are not changed.
  • Off means by hand. If you leave it off, completing every task under a routine does not close the routine, and it still shows as outstanding until someone marks it Done. Build that into your weekly review.
  • Look at the tasks, not only the routine. A routine at Done tells you every task was resolved, not that every inspection passed. Check the inspections and any defects they raised for what was actually found.